Lane Cove Works Update

Calendar Mark Streamline Icon: https://streamlinehq.com

July 8, 2020

With the centre partially open, we have still been able to tick off some further upgrades around our centre. Below is a list of work that has occurred in the last month and a half: Complete Steam Room fit out including internal walls, lighting and seating Complete regrout of Spa Pool Spa Pool tile repair Spa/Sauna/Steam Room's shower area tile replacement Replacement of a number of cracked poolside tiles Emergency door push bar repair on a number of emergency exits Health Club female and male change room's hydraulic door closer replacement Heat gun removal of glue patches around the centre With more to come, stay tuned...